If you’re planning a post-frame accessory building in Maurice, Louisiana (ZIP code 70555), the permitting process works a little differently than in other parts of the state. Because this area covers portions of Vermilion Parish and the Village of Maurice, it’s important to understand the specific rules that apply before construction begins.
Mallett Buildings handles the construction, but the permit must be obtained by the property owner and knowing what your parish requires will help you avoid delays.
Below is a clear overview of what customers in the 70555 Maurice area should expect.
1. Determine Whether You’re in Maurice City Limits or Unincorporated Vermilion Parish
ZIP code 70555 includes:
- Areas inside the Village of Maurice
- Areas outside city limits within Vermilion Parish
Each has slightly different permitting processes.
If you’re unsure, we can help point you to the proper office or you can check your tax bill or parish parcel map.
2. A Permit Is Required for All Accessory Buildings
Whether your building is going in city limits or parish jurisdiction, a construction permit is required for accessory structures such as:
- Post-frame buildings
- Metal shops
- Barns
- Storage buildings
- Garages
- RV covers
This includes buildings with or without utilities.
3. What Vermilion Parish Requires (Most Common for 70555)
If your property falls under the Vermilion Parish Police Jury, here’s what the parish requires for accessory buildings:
✔ Engineered Plans for Post-Frame & Metal Buildings
Because Mallett Buildings constructs engineered post-frame structures, Vermilion Parish requires:
- Stamped engineered drawings
- Wind load design specifications
- Foundation/anchoring details
- Truss engineering
This is mandatory for metal and post-frame buildings.
✔ Required Setbacks
Minimum distances from property lines:
- 25 ft from the road right-of-way
- 5 ft from side property lines
- 15 ft from rear property line
You must show these on your site plan.
✔ Site Plan
Your permit application must include a drawing showing:
- Lot dimensions
- Location of the proposed building
- Existing structures
- Driveways
- Utility routes
- Easements or servitudes
This does not need to be complicated, just accurate.
✔ Flood Zone Requirements
If your property is in a flood zone:
- A Preliminary Elevation Certificate is required
- Engineered foundation plans may be needed (especially for V or VE zones)
- A Final Elevation Certificate is required before occupancy
If you aren’t sure about your flood zone, we can help you determine this early.
✔ Soil/Fill Requirements
If you plan to bring in fill:
- Clean sand/gravel over 24 inches requires a compaction test
- Dirt/earth fill over 8 inches requires compaction documentation
This ensures the slab is built on stable ground.
4. If You’re Inside Maurice City Limits
The Village of Maurice may require:
- Permit application through City Hall
- Zoning compliance check
- Review of setbacks and site layout
- Approval before construction begins
Most customers in 70555 fall under the parish, but city-limit properties must follow municipal requirements.
5. Don’t Forget About Utilities
If your building will include power, water, plumbing, or a slab with utilities underneath, those plans must be finalized before the concrete phase.
The parish will want to know whether your building includes:
- Electrical
- Plumbing
- Wastewater connection
- Any future utility additions
Utility planning affects:
- Slab design
- Underground conduits
- Plumbing placement
- Inspection scheduling
6. Inspections Are Required
Vermilion Parish uses contracted inspectors, and you’ll be responsible for:
- Calling in each required inspection
- Having permit documents on-site
- Ensuring the building location matches your approved site plan
We’ll guide you through what needs to be ready, but inspections must be coordinated by the property owner or contractor of record.
Preparing for a Smooth Build
For Mallett Buildings customers in the 70555 area, here’s what you should do before we schedule your delivery and framing:
✔ Pull your permit early
✔ Have your site plan ready
✔ Confirm setbacks and lot lines
✔ Check your flood zone
✔ Finalize utilities before concrete
✔ Keep your permit posted on-site
This ensures your project stays on schedule and eliminates the most common permitting delays we see in Vermilion Parish.
We’re Here to Help